Region 4 Board of Education John Winthrop Security Project Building Committee · August 7, 2025

The Region 4 (John Winthrop Middle School) Security Project Building Committee met Aug. 7, 2025, approved Orlando Annulli & Sons Payment Application #3 for $223,020 and Change Order Proposal #8 Rev1 for $43,644.92, heard a construction update that put the project about 2–3 weeks behind schedule, and discussed contingency uses including security equipment and access controls.