JWMS Security Project Building Committee Meeting Minutes From 05 pdf

Region 4 Board of Education John Winthrop Security Project Building Committee · May 28, 2026

The Region 4 Board of Education John Winthrop Security Project Building Committee met remotely May 28, 2026, and unanimously approved an Orlando Annulli & Sons change order of $31,760.86 to add elevator and lobby cooling, and the purchase of two environmental sensors for $1,399.12. The committee discussed scheduling future meetings and adjourned at 8:42 a.m.