The Capital Projects Committee met June 24 to review final construction-phase and collection-system contracts for the wastewater/treatment project, approve edits that removed the RPR from GHD's scope (producing roughly $700,000–$750,000 in savings), and vote unanimously to recommend that the Select Board award the listed contracts pending SRF approval.