The Fort Pierce Utilities Authority board met July 7, 2026, and approved a $3.28 million amendment to a wastewater conveyance contract and a roughly $2.59 million purchase of replacement transformers for the Totten Substation; staff also presented the 2025 actuarial report showing the retirement plan funded ratio near 80%.