Market Blvd. Improvement Project Update - Early July 2026

City Public Works · July 7, 2026

Charlie Holly, the city's public works director and city engineer, gave an update on the Market Boulevard reconstruction project. He said phase 1 is complete, phase 2 begins Monday, July 6 and will close the corridor at the railroad crossing through much of the summer, and one block between Jimmy John's and Wendy's was deferred to phase 3 because of underground utility conflicts.