At a Public Service Commission hearing, a company witness identified as Mister Latham answered commissioners' questions about site selection, interconnection, battery duration and safety for a proposed 500-megawatt battery storage project. Commissioners pressed the company on brownfield siting, whether it had consulted BGE about grid constraints, and emergency response measures; the session adjourned until the next day.