Officials say pool project is on track for December completion

Sep 15, 2026

Staff reported beams salvaged from the old pool will be used in the concession stand ceiling, major plumbing work will be completed in about 2–2.5 weeks, and the project remains on schedule for a December finish.

The full story

City staff updated the council on the municipal pool project, saying crews have started significant work and that reclaimed boards cut from the old pool will become part of the concession-stand ceiling. "We did receive back the boards that we cut beams from the old pool and those will be used in the ceiling of the concession stand area," the mayor said, and staff estimated two to 2.5 weeks for large plumbing tasks between the pool shell and bathhouse.