Nutter Fort engineering report: Nutter Run complete; Chub Run progress and Phase II AML bidding set

Jul 28, 2026

Engineers reported the Nutter Run project is complete pending water-sampling results, Chub Run sewer work is progressing and being synchronized with a new wastewater plant, and Phase II AML pre-bid and bid-opening dates were set for late August and early September 2026.

The full story

Town engineering staff reported that the Nutter Run project is complete and that samples will be taken on Thursday for testing before the project is placed in service, pending acceptable results. The Chub Run sewer project is progressing well; engineering said its schedule and activation are interdependent with a new wastewater treatment plant on the opposite side of the interstate, and the contractor has been offered a time extension to align the two systems' activations.