Surveyor reports progress on drain reconstructions; Board executes corrected Banning contract for J.S. McCarty Phase 2

Aug 24, 2026

The Board executed a revised contract with Banning Engineering that includes utility coordination for J.S. McCarty Drain Phase 2 work, accepted a $26,633.40 performance bond for erosion control, and heard project‑by‑project construction updates including progress on Ingerman, J.S. McCarty Phase 3 and Emily Vestal drains.

The full story

The Hamilton County Drainage Board executed a corrected professional services agreement with Banning Engineering for construction‑related services on the J.S. McCarty Drain Reconstruction Phase 2 (Banning). County staff said the version the Board previously signed omitted utility coordination; the revised contract includes that service and was approved unanimously.