DPW updates board on culvert replacement timeline; partial funding in hand
Sep 15, 2026
DPW said the partially collapsed culvert over Mongei Brook (Aaron/Wrentham Road) identified in 2023 remains under a single‑lane alternating configuration, that design/permitting is advancing, and that construction advertising is targeted before next May town meeting though total construction OPCC exceeds the $500,000 previously earmarked.
The full story
DPW briefed the Select Board on the status of the culvert replacement on Aaron/Wrentham Road over Mongei Brook, first identified as partially collapsed in July 2023. The town has maintained the roadway in a single‑lane, alternating‑traffic configuration since that time while design and permitting proceed.