The Board reviewed a revised long‑range plan: a traffic-calming project completed at $26,739, a backup irrigation well near completion at $291,500 expected to be primary, monument replacements estimated at $250,000, and gatehouse renovation estimates that, combined with CIP changes, may require a $2.5 million loan.

The full story

Eric Long, PSGRC General Manager, reviewed a revised Long Range Plan at the April 28 meeting. He reported the Traffic Calming Project (radar sign and traffic camera) was completed at a total cost of $26,739 and said the backup irrigation well project is near completion with an additional‑well cost of $291,500; he expects the new well to become the CDD’s primary well.