Work group debates water‑use limits for data centers and WUE metric
Sep 15, 2026
Sep 15, 2026
Members discussed how to measure and limit data‑center water consumption, citing industry WUE ranges (0.05–0.2 L/kWh) and Amazon's reported 0.18 L/kWh, questioned whether negotiated WUE targets give the county enough leverage, and explored impact‑zone analyses and reliance on utilities to assess capacity.
The full story
The APC work group spent substantial time on how the draft zoning ordinance should address water use by large data centers.