Hall County courthouse construction reports progress; project ~35% expended

Jul 14, 2026

County officials reported roofing, windows, and framing complete on much of the new courthouse, with systems installed and the project about 35% expended to date; a walkthrough of the second floor was scheduled to identify adjustments.

The full story

A county official provided an update on the ongoing courthouse construction: the roof and windows are installed, the first and second floors are framed, air handlers and mechanical systems are in place, and basement work is essentially complete aside from finishing items. Officials scheduled a second-floor walkthrough later in the week to identify required refinements.