Mission Frontage sidewalks to proceed; paving delayed after utility conflicts
Sep 17, 2026
Sep 17, 2026
Public-works staff said utility locations forced a pause in Mission Frontage paving; crews will finish sidewalks and swales by late October while paving may be postponed until spring after utility relocations are completed.
The full story
Public-works staff updated council on the Mission Frontage project, saying crews put up traffic control and began work but then found communications and power utilities higher than expected, which paused the paving work. “We were really hoping to get the Mission Frontage project started this last week... Right now, we're in a pause because we've located those utilities,” Ben said.