Applied Connective presented a server replacement plan and recommended issuing an RFP for hardware while the vendor handles installation; lead time for a new server is about three months and quotes for backup internet will be sought.
The full story
Applied Connective representative Matt Childress presented a preliminary Request for Proposals for the county's server replacement on Sept. 8 and recommended soliciting bids for hardware while retaining Applied Connective to perform installation and migration work. Childress said the prior proposal totaled about $33,000, with approximately $23,000 attributable to hardware, and that current lead time for new servers is about three months.