Officials outline procurement, progressive design‑build approach and 2028 construction target

Sep 17, 2026

WSDOT and program staff described progressive design‑build procurement steps — RFQ now, RFP in November, proposer shortlists in spring 2027 — and estimated the major design‑build contract at $3.3–3.9 billion with a target to begin bridge construction in 2028 and pre‑completion tolling live in 2028.

The full story

Program delivery staff told the joint committee that procurement for the first funded phase will use a progressive design‑build model intended to share risk and encourage collaboration with industry.