The draft UDO amendment would require a decommissioning plan and financial assurance (minimum $75,000 floor or 1.25× the engineer estimate), Tier‑4 emission standards for generators (or equivalently stringent standards), and a preference for closed‑loop cooling to limit water use.
The full story
Planning staff’s draft ordinance would require an applicant for a data processing facility to submit a decommissioning plan and a financial assurance instrument held by the county to guarantee site restoration. The draft sets a minimum guarantee of $75,000 or 1.25 times an engineer’s estimated decommissioning cost, whichever is greater; board members questioned whether the $75,000 floor was sufficient for large facilities.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →