Developer outlines Seminole pumped-storage plan; DEQ issues 401 certification with conditions

Apr 7, 2026

R Plus presented a proposed 970-MW pumped-storage project at Seminoe Reservoir that would add a 120-acre upper reservoir and a 29-mile transmission line; company said Wyoming DEQ issued a 401 water-quality certification contingent on monitoring and adaptive limits to prevent temperature impacts downstream.

The full story

R Plus presented a technical briefing April 7 on the Seminole pumped-storage proposal, a large-scale energy-storage project the company says could store roughly 10,000 acre‑feet per full 12‑hour cycle and deliver about 970 MW for up to 12 hours. The developer described an underground powerhouse, a 120‑acre upper reservoir (13,000 acre‑feet total capacity with about 10,000 acre‑feet active), and a roughly 29‑mile transmission line to the Aeolus substation. Company officials estimated a multi‑billion‑dollar capital investment and said construction would create hundreds of jobs during a five‑year build period if the project proceeds.