River Ridge reports drainage work underway at four sites; tree removals and July completion targeted
Jun 23, 2026
District Engineer Charlie Krebs told the Board that all four drainage sites are under construction with pipe, grading and fill staged; Palmetto Dunes will need 12 tree removals and Turnberry/ Oak Run work is scheduled through early July, with completion anticipated by the end of July.
The full story
Charlie Krebs, District Engineer, told the Board that "all four sites are under construction; sites are cleared and silt fences were installed." Work includes pipe installation, grading, staged fill and sod installation; Palmetto Dunes requires removal and replacement of 12 affected trees (mostly slash pines and two red maples). Krebs said Palmetto Dunes is expected to be completed by the end of the week and the overall project is expected to be completed by the end of July if grading is finished on schedule.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →