Chandler Road reconstruction delayed a week; sewer work to take precedence
Jun 16, 2026
Jun 16, 2026
Deputy superintendent told the board the Chandler Road project is delayed one week, initial work focuses on sewer repairs and paving is expected next year. Emergency access and detours will be coordinated with the County Road Commission.
The full story
The board heard an update on the Chandler Road reconstruction project: work start was pushed back one week because of unforeseen startup issues, and the early phase will focus on underground sewer work with major paving deferred until next year.