Citizen Portal

Board authorizes expanded PSE interconnection study for behind-the-meter generation

Zeeland Board of Public Works Commission · September 15, 2026

Summary

The Board authorized Power System Engineering to complete a revised Phase 2 interconnection analysis for up to $30,000 and empowered staff to proceed with Phase 3 for up to $15,000, keeping total study spending (including completed Phase 1) under $71,622.

Electrical Transmission & Distribution Manager Coots updated the board on the behind-the-meter generator (BTMG) interconnection study and recommended PSE complete a detailed Phase 2 evaluation focused on accommodating 50 MW of generation and identifying required capital improvements. Phase 2 is estimated at $20,000–$30,000 and Phase 3 at $10,000–$15,000.

The board authorized the revised Phase 2 scope for an amount not to exceed $30,000 and delegated authority to staff to proceed with Phase 3 for up to $15,000 if staff determine the additional analysis is warranted; combined with completed Phase 1 work ($26,622), total study expenditures will not exceed $71,622, below the $88,000 budget identified in April.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source