McCormick Road work could be delayed as utility relocates lag
Sep 17, 2026
City staff told council a utility‑location/relocation issue may delay McCormick Road construction; a staff‑engineer meeting with the contractor is scheduled to assess whether work can proceed without relocates and when to issue a notice to proceed.
The full story
Public works staff provided an update on the McCormick Road project, warning on Sept. 16 that one utility’s locate and relocation work remains unresolved and could cause a delay to the city’s notice to proceed.
Brian (speaker 16), introduced earlier by staff as the project lead, said staff and the contractor will meet to "go through every section of conflict" to evaluate whether crews can safely work while the utility remains in place. He emphasized the city does not want to authorize material orders and start contract clocks until relocation issues are clear.
Council and staff fielded questions about road closures and traffic impacts; Brian said the project will require full shutdowns of the corridor at times and that restaurants would have limited access during closures. He cautioned that the timeline depends on securing utility cooperation and resolving relocation schedules.
The update did not include a new firm start date; staff said they will return to council with timing after the scheduled meeting with the contractor and utility.