A remote project representative briefed Pratt County commissioners on road-use agreements, decommissioning security increases, insurance corrections (Pratt County name typo), completed preconstruction inspection, a June 23 on-site kickoff and a delay in battery delivery to late September–early October with overall completion currently slated for April 2027.

The full story

A project representative appearing remotely identified as Cody updated the commission on preconstruction work for a proposed battery-storage facility and answered commissioners' procedural questions about road-use and decommissioning agreements.