Commissioners approve $70,870.75 change order for 2026 paving program

Sep 8, 2026

Fayette County approved Change Order No. 1 with Cox Paving, LLC, increasing the 2026 paving contract by $70,870.75 to a revised contract price of $1,566,378.45; completion time unchanged.

The full story

The Fayette County commissioners approved Change Order No. 1 for the 2026 Fayette County Paving Program on Sept. 8, authorizing additional quantities and one mill-and-fill item. The change order adds $70,870.75 to the original contract price with Cox Paving, LLC, revising the total to $1,566,378.45; the time for completion was unchanged.