High school update: windows installation, elevator progress and $1.8M in potential change orders
Sep 17, 2026
Sep 17, 2026
Owner's representative reported that exterior windows for the high school are on‑site and installation will begin soon; masonry work is largely complete, the elevator installation is underway and estimated potential change orders total about $1.8 million, mainly tied to welding shop changes.
The full story
The owner's representative provided an update on the high school construction progress, describing completed masonry, an elevator installation progressing with a working platform and an upcoming exterior window installation. He said a mock‑up was installed several weeks earlier and that crews should begin installing windows next week.
