Board approves $399,929.97 pay application for Secondary Roads admin addition

Jan 6, 2026

Turner Pay Application #13 for the Secondary Roads Administration addition, covering work through Dec. 31, 2025, for $399,929.97 was approved; the project is 77% complete with 54% remaining contingency and 20% remaining allowance.

The full story

The Dallas County Board of Supervisors approved Turner Pay Application #13, totaling $399,929.97, for work completed on the Secondary Roads Administration addition through Dec. 31, 2025. County staff reported the exterior storefront is installed, the PEMB overhead door height modification is complete, interior painting has started and overhead MEP rough‑in is 95% complete.