Drainage improvements underway at four River Ridge sites; crews working evenings and Saturdays
Jun 23, 2026
Jun 23, 2026
District Engineer reported all four drainage sites are under construction with piping, grading and silt fences in place; several trees will be removed and replaced and staff expect project completion by end of July if grading remains on schedule.
The full story
District Engineer Charlie Krebs reported that all four drainage-improvement sites are under construction: sites are cleared, silt fences installed, pipes placed in the ground and fill staged, with grading and fill completed in Turnberry. Krebs said Palmetto Dunes is expected to be completed by the end of the week and that sod will likely be installed in Turnberry and Palmetto Dunes the week of July 2. He added that pipe work in Oak Run is scheduled for the week of June 29.