Committee shifts $293,441 from construction contingency into technology budget

Sep 21, 2026

To cover a previously approved server/technology purchase and a small AV cable change order, the committee voted to transfer $293,441.74 from construction contingency into the technology line; the motion passed unanimously.

The full story

Staff told the committee that a previously approved technology package ($286,908) and a newly identified ProAV change order ($6,533.55) would be covered by a single budget revision that moves $293,441.74 from the construction contingency into the technology budget. The transfer was presented as a consolidated request to avoid multiple small draws from several budget lines.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in