Committee shifts $293,441 from construction contingency into technology budget
Sep 21, 2026
To cover a previously approved server/technology purchase and a small AV cable change order, the committee voted to transfer $293,441.74 from construction contingency into the technology line; the motion passed unanimously.
The full story
Staff told the committee that a previously approved technology package ($286,908) and a newly identified ProAV change order ($6,533.55) would be covered by a single budget revision that moves $293,441.74 from the construction contingency into the technology budget. The transfer was presented as a consolidated request to avoid multiple small draws from several budget lines.