Engineer reports water-system progress, well drilling and meter upgrades
Jan 8, 2024
City engineer Brad Baird reported the Columbia River water system is about 60% complete and should be ready for summer implementation pending testing; well drilling is underway but encountered rock; a remote meter replacement project is scheduled for April with 31 test meters currently in place.
The full story
Brad Baird of Anderson Perry & Associates briefed the council on six infrastructure items. On the Columbia River water system he said it is "probably crowding up to 60% right now" and that it should be ready for implementation this summer. He reported well drilling is underway but encountered unexpected rock early in the bore; testing will take about three weeks to determine viability.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →