Construction update: Crosby ISD reports progress on 6th‑grade campus and Red Barn project

Sep 22, 2026

Director of construction Carlos Amiano said the 6th‑grade campus is receiving steel and the detention pond is about 95% complete; the Red Barn/White Barn scope is at 100% development and administrative building bids are under review.

The full story

Carlos Amiano, the district’s director of construction, told trustees that the administrative building has a permit and staff expects to review bids this week with a recommendation to the board in November. He said the Red Barn and White Barn scope has been refined to include just those two structures and is at 100% development.