Downes reports defective flow sensor; Testing and Balancing set for March 23
Mar 16, 2026
Downes Construction reported a defective flow sensor that must be replaced before SWAN completes wiring; Testing and Balancing is scheduled for Monday, March 23. Committee members warned commissioning timing could add costs if delayed.
The full story
Downes Construction informed the committee that a defective flow sensor needs replacement and that SWAN will complete wiring work prior to Testing and Balancing. Downes’ M. Carlson stated that Testing and Balancing "will be completed next Monday, March 23rd." The work is a prerequisite for final commissioning.
Committee members and the design team discussed potential impacts on the commissioning schedule and costs. Chair M. Callahan warned that delays could add expense and suggested there "may need to be a hiatus on the timing" to ensure systems are fully commissioned. The committee recorded the update and continued to monitor Testing and Balancing results before final acceptance of the HVAC scope.
Written with AI from the event video and transcript. Check it against the source ↓