Evergreen Elementary construction on track despite brief permit review delay; roof targeted by year-end

Sep 21, 2026

District staff and contractors reported framing and slab pours underway for Evergreen Elementary. City permit review required a third‑party reviewer but allowed selective work to continue; the project team is targeting roof completion by year’s end.

The full story

District staff and project contractors gave the board a construction update for Evergreen Elementary, saying site work, underground utilities and foundation slabs are complete in sections and framing is underway. "Since breaking ground in June, we've gotten a lot of our civil infrastructure in... we've gotten our fire hydrants," Noah Nudell, the project superintendent for CoorsMo, told the board.