Board approves $16,196.76 payment for middle‑school auditorium lighting work
Aug 17, 2026
The board approved invoice #8179 from AV Solutions for $16,196.76 for ongoing middle‑school auditorium lighting/control‑board work; the administration said the project is partially complete but several parts remain to be ordered.
The full story
The board reviewed and approved payment of AV Solutions invoice #8179 for $16,196.76 for middle‑school auditorium lighting and control‑board work previously approved on April 20, 2026. Administration told the board the project is not fully complete; relays and some control‑board work have been performed but additional parts are on order to finalize the system.