Selectboard approves phased paving plan with DNF, schedules guardrail work

Sep 8, 2025

The Goshen selectboard agreed to stage paving with contractor DNF — a first coat this fall and a finish coat in spring — to allow culverts to settle. Members also approved guardrail installation (quoted at $10,000 for used/brown material) and discussed how Phase 1 Townhills funds will be applied to road accounts.

The full story

The Goshen selectboard agreed to a phased paving approach with contractor DNF that will place a first driving course before winter and a final wearing coat in spring to allow culverts and shoulders to settle. Chair (S1) said the first layer now will let crews patch any cracks before the final coat is applied in better weather.

S1 explained the rationale: "DNF suggested that we only do the 1st coat the yes. The 1st layer for winter and then do the finished coat in the spring... It's a much smarter move and investment of our money to wait because then if something does crack, that can be fixed and patched before putting the final coat on in the spring." Staff member (S3), who oversees road work, confirmed chloride treatment and grading are ongoing and that secondary roads will be completed next month.

The board also discussed guardrail placement and cost options. S1 reported a contractor quote of 508 linear feet for a used brown (rusted) guardrail at $10,000 versus $15,000 for new silver rails; members signaled preference for the lower-cost brown option and S3 said he will mark the actual guardrail locations before installation. The board directed staff to confirm quotes and timing so guardrail work can occur before winter.

Written with AI from the event video and transcript. Check it against the source ↓