Drainage projects underway across River Ridge; crews working nights and weekends, completion expected by end of July

Jun 23, 2026

District Engineer reported all four drainage sites are under construction, with sod and pipe installation schedules and tree removals planned; staff will monitor sheet-flow changes and track additional contingency costs from unexpected damages.

The full story

Charlie Krebs reported that crews have cleared all four drainage sites, installed silt fences, staged fill at Turnberry, and begun pipe and grading work. He said sod is likely to be installed the week of July 2 in Turnberry and Palmetto Dunes and that pipe work in Oak Run is scheduled the week of June 29; if grading is completed on schedule, the overall project is expected to be completed by the end of July.