Committee holds $585,000 contractor requisition pending backup and corrected schedule
Sep 21, 2026
Sep 21, 2026
The committee declined to approve a large contractor requisition as submitted, citing missing subcontractor schedule-of-values, unclear bonding documentation and unacceptable schedule logic; staff and consultants proposed a short virtual follow-up meeting to resolve the items.
The full story
The committee reviewed a requisition submitted by the general contractor for $585,000 and declined to approve the full amount at this meeting, citing missing or unclear supporting documentation.