ATP outlines FTA timeline, risk workshop and contingency options for light-rail entry to engineering

Aug 19, 2026

ATP staff said the project has completed NEPA and aims to request FTA entry into engineering in mid-2027; staff described planned risk workshops with FTA and contingency tools such as staged authorizations, letters of no prejudice, and monthly reimbursement contracts if federal action is delayed.

The full story

ATP executives told the board that the light-rail program has completed major federal steps for project development and is working toward requesting entry into the engineering phase of the FTA Capital Investment Grants (CIG) program.