Board approves immediate concrete patching for utility cuts after Milestone declines
Jun 2, 2026
Board heard that 15 street cuts from utility work need concrete topping to prevent settlement; because Milestone would not include the patches in the CCMG paving contract, the board approved hiring Myers to complete concrete patching now.
The full story
Chair explained that multiple cuts from recent utility work (about 15) require concrete topping to prevent new asphalt from settling into the patches. He said the engineer advised against adding these patches to the CCMG contract because paving quantities were already overrun and that the contractor Milestone declined to add the work.