Engineers advise pausing Lighthouse Drive reconstruction until vulnerability and adaptation planning is complete
Apr 13, 2026
Finley & Horn engineers reported muck layers 7–10 feet below Lighthouse Drive causing differential settlement and recommended delaying reconstruction until the town's vulnerability assessment and adaptation plan inform a phased, grant‑funded solution.
The full story
Bert King of Finley & Horn outlined geotechnical work on Lighthouse Drive, saying borings found organic 'muck' layers about 7–10 feet below the road that are compressing and causing differential settlement. He said full excavation to remove the muck would require prolonged road closures and be highly disruptive to residents, and recommended either installing a geogrid beneath new pavement as an interim stabilizing measure or waiting for the adaptation plan and potential grant funding.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →