Board discusses gatehouse, monument replacement and a potential $2.5M loan

Apr 28, 2026

Staff presented Long Range Plan estimates: monument replacements at $250,000 and gatehouse renovations estimated at $615,775 for FY2026 and $407,240 for FY2027; the board noted the gatehouse project exceeds the $550,000 sealed‑bid threshold and said CIP changes may require approximately a $2.5 million loan.

The full story

District staff reviewed updates to the Long Range Plan, including monument replacements and gatehouse renovations. Mr. Long said he maintained an estimate of probable cost of $250,000 to replace four neighborhood monuments and presented gatehouse renovation estimates of $615,775 for fiscal year 2026 and $407,240 for fiscal year 2027.

Because the gatehouse estimate exceeds the $550,000 sealed‑bid threshold, staff said the CDD will be required to proceed with a sealed‑bid process for that project; monument work would not require sealed bids at the current estimate. Mr. Krebs will submit permit applications to the Village of Estero and staff plans to bid the gatehouse and monument projects similarly to the stormwater effort.

Mr. Long and staff noted that the overall change in the CIP will necessitate planning for a construction loan of approximately $2.5 million. Mr. Adams said he will meet with Gulf Coast Business Bank to obtain a term sheet for a possible construction loan, with Costs of Issuance estimated at $50,000.

Written with AI from the event video and transcript. Check it against the source ↓