The board authorized a payment application of $267,935.55 for the East End Reconstruction project covering work from May 1 to June 19, 2026; retainage was held per contract documents and no change orders were reported for this payment request.

The full story

At the Village of Ellsworth Special Village Board meeting on June 24, 2026, the board approved a payment application for the East End Reconstruction project in the amount of $267,935.55. The application covered work completed from May 1, 2026, through June 19, 2026, and included retainage in accordance with the contract documents. Trustee Borner moved the payment approval and Trustee T. Hines seconded; the motion carried "without a negative vote."