Route 28 water-main work delayed as MassDOT schedule forces plan changes

Oct 21, 2025

MassDOT accelerated adjacent work on Route 28, requiring the town to revise plans and connect to an existing water main at the Haron River Bridge; commissioners said they are seeking clarity on oversight and hope to have permit results by mid-November.

The full story

Commissioners were told that MassDOT advanced work on the west portion of the Route 28 project, which forced the town to revise its connection plans where the line ties into the existing main at the Haron River Bridge. The chair said the town had been planning to bid its portion first but had to rework drawings and permitting after the state moved ahead on its section.