County approves increased engineering compensation for Dutch Edge Lane reconstruction
Mar 18, 2026
The board approved an amendment to the engineering services agreement for Dutch Edge Lane reconstruction, increasing additional services compensation by $294,700 to a not-to-exceed total of $594,700 to cover construction oversight after lower-than-expected bid results.
The full story
County staff presented an amendment to the professional services agreement for the Dutch Edge Lane reconstruction project. The engineer indicated bid prices came in roughly $1,000,000 under an earlier estimate; additional construction oversight and related services were needed. The amendment increases compensation for additional services by $294,700, not to exceed a revised $594,700 cap.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.