Quarterly bond update: Pershing and Bingham projects show progress; safe‑room work starting

Sep 23, 2026

Staff reported progress on multiple bond projects: Pershing Middle precast work is complete and storm‑shelter installation is scheduled, Bingham Elementary has completed precast footings and precast panels are starting; staff said many projects are wrapping up on schedule.

The full story

Deputy Superintendent Doug Van Zyl briefed the board on bond and construction activity across the district. He said Pershing Middle School’s precast is complete, underground mechanical and plumbing work is finished and more than 50,000 square feet of concrete has been poured; safe‑room panel installation at Pershing was due to begin on the 28th and the first steel delivery was expected the following day.