Quarterly bond update: Pershing and Bingham projects show progress; safe‑room work starting
Sep 23, 2026
Staff reported progress on multiple bond projects: Pershing Middle precast work is complete and storm‑shelter installation is scheduled, Bingham Elementary has completed precast footings and precast panels are starting; staff said many projects are wrapping up on schedule.
The full story
Deputy Superintendent Doug Van Zyl briefed the board on bond and construction activity across the district. He said Pershing Middle School’s precast is complete, underground mechanical and plumbing work is finished and more than 50,000 square feet of concrete has been poured; safe‑room panel installation at Pershing was due to begin on the 28th and the first steel delivery was expected the following day.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →