Council approves $1.05 million contract for fall sidewalk program
Sep 8, 2026
The council adopted R‑2026‑66 to award Agreement No. 639 to Schroeder & Schroeder, Inc. for the 2026 Fall New Sidewalk Program, authorizing up to $1,047,700 plus a 10% contingency to install nearly 14,000 feet of sidewalk; staff said the lowest bid was under budget.
The full story
Wheaton City Council on Sept. 8 adopted Resolution R‑2026‑66 authorizing Agreement No. 639 with Schroeder & Schroeder, Inc. for construction of the 2026 Fall New Sidewalk Program for a total amount not to exceed $1,047,700, plus a 10% contingency.
City Manager Raymond Munch and Director of Engineering Joseph Tebrugge reported that engineering staff planned nearly 14,000 feet of new sidewalk this fall and that seven bids were received with the lowest under budget. Munch said the program continues the City’s effort to create a comprehensive sidewalk network. The resolution passed unanimously on roll call.
The council also adopted an Illinois Highway Code resolution (R‑2026‑67) required by the Illinois Department of Transportation before expending State Motor Fuel Tax funds for the sidewalk project.
Written with AI from the event video and transcript. Check it against the source ↓