Final change order returns $51,210 and sets Courthouse Window Replacement at $918,790
Jun 4, 2026
Jun 4, 2026
The Board approved Change Order #004 (Final) for the Courthouse Window Replacement Project, returning $51,210 to the contingency and establishing the final contract sum at $918,790.00 under Resolution No. 26-06-619.
The full story
Resolution No. 26-06-619 authorized Change Order #004 (Final) for the Courthouse Window Replacement Project. The change order returns the remaining $51,210.00 from the General Contract A Contingency Allowance and sets the final contract sum at $918,790.00. The Board voted unanimously to approve the final change order.