Council approves closeout tasks and multiple contractor claims for Community Crossings projects

May 19, 2026

Council was updated that the 2025 Community Crossings milling is substantially complete and approved contractor pay applications and claims, including a $250,000 payout to Johannemann Excavating and approval of task orders for future Community Crossings grants.

The full story

Rachel, representing Community Crossings work, told the council that milling is complete and that additional asphalt patching was required in areas where milling exposed minimal asphalt depth; full closeout is expected within a month. Council approved a series of claims and pay applications tied to the project and related work.