County facilities update: engineer's office move, compressor delivery and window delays

Sep 22, 2026

Facilities staff told the board the engineer's office move is nearly complete, carpeting and painting are scheduled, a rooftop compressor arrived but lift/weather may delay installation, and window work is paused by wet ground conditions with contractors agreeing to repair damage.

The full story

Dave gave a facilities update noting the engineer’s office is nearly moved and painting and carpeting are scheduled in the coming weeks. He told supervisors crews will try to schedule the south side work last to avoid conflicts, and that contractors recognized wet ground conditions that could cause temporary damage but agreed to repair impacted areas.