Board reviews Long Range Plan; backup irrigation well near completion, CIP changes may require $2.5M loan
Apr 28, 2026
The board reviewed a revised Long Range Plan showing traffic-calming completed ($26,739), a near-complete backup irrigation well costing $291,500, monument and gatehouse cost estimates, and a projected need for about $2.5 million in financing to cover capital plan adjustments.
The full story
Eric Long, PSGRC General Manager, presented a revised Long Range Plan and reported several capital items. He said the Traffic Calming Project (radar sign and traffic camera) cost $26,739 and is complete. On the backup irrigation well, Long reported a project cost of $291,500 and said the project is near completion; he expects the current pump to be installed and operating within the next couple of weeks and plans to perform water-quality testing on both wells.