District plans 2027 network switch update, expects substantial E‑rate support

Sep 8, 2026

Technology committee outlined a districtwide network‑switch replacement planned for 2027, with an estimated cost above the prior $320,000 project and anticipated E‑rate Category 2 reimbursement of roughly 80–85%; administration will run a parts mini‑bid this November and seek board contingency approval in early 2027.

The full story

Mr. Hill told the technology committee the district must plan its next network‑switch replacement now because the last upgrade was in 2019 and equipment life is about 6–8 years. He said administration will develop a parts list, run an E‑rate mini‑bid in November, review bids in December, put a contingent bid approval on the board agenda in Jan–Feb 2027, and target installation for summer or fall 2027.